For infrastructure, East Coast Railway has been sanctioned an amount of Rs. 11495.90 Crs (Including Rly.Electrification funds exclusively allotted to ECoR) for the year 2024-25. Decrease of 0.2% over last year (Last Year Rs.11513.74 Cr). However, there is an increase of Rs. 1127.06 Cr under Budgetary resources over last year(11.2%)
For New line, the Budgetary grant for 2024-25 is Rs2812.91 Crs, (LY- Rs2848.20Cr i.e. 1% less than last year Budget allotment )
For Doubling, the budgetary grant for 2024-25 is Rs.3818.22 Cr, (LY- Rs. 3834.46 Cr i.e. almost same to last year Budget allotment )
For Traffic Facilities the budgetary grant is Rs 200.70 Crs for the year 2024-25. (LY- Rs.147.39 Cr i.e. 36% more than last year Budget allotment). Provision for safety fencing and subways on various routes with speed 130 KMPH and above, sanctioned cost of Rs 1135 Cr with token allotment.
For Road over Bridges/Road under Bridges, the budgetary grant for 2024-25 is Rs 486.76 Cr.
For Track Renewal, the budgetary grant for 2024-25 is Rs. 931.55 Crs, (LY- Rs.935.73 Cr almost same to last year Budget allotment )
For Bridge Work, the Budgetary grant for 2024-25 is Rs. 170.04 Crs, , (LY- Rs.97 Cr i.e75 % more than last year Budget allotment ).
For S&T Works, the budgetary grant for 2024-25 is Rs. 247.94 Crs, 31% decrease over last year (Last Year– Rs. 357.97 Cr).
· 05 New works sanctioned under Plan Head -35 (Railway electrification) for upgradation of Railway electrification under ECoR jurisdiction. The same will be executed by ECoR. Allotment under PH-35 (Railway Electrification) to ECoR is Rs 269.11 Cr
For Customer Amenities, the budget grant for 2024-25 is Rs 671.40 Crs,) 12% Decrease over last year (Last Year– Rs 763.98 Cr). Total Provision for Major upgradation of station is Rs 399.16 Cr ( For Phase-I Rs 169.49 Cr , Phase-II Rs 204.64 Cr, Phase-III Rs 25.03 Cr) and for Amrit Bharat Station Scheme Rs 208.86 Cr.
1 Plan Outlay 2024-25
BG 2022-23
BG 2023-24
BG 2024-25
Excess over LY (in Amount)
Excess in % over LY
ECoR (Railway)
8187.17
9892.84
10385.49
492.65
5%
RVNL
2129.03
1620.90
1110.41
-510.49
-31%
Sub Total ECoR
10316.20
11513.74
11495.90
-17.84
-0.2%
Rly Electrification (Executed by CORE)
66.92
126.75
66.5
-60.25
-48%
Total ECoR (Incl.RE)
10383.12
11640.49
11562.4
-78.09
-0.7%
Budgetary Allocations for important ongoing NEW LINE projects:
SL
Name of Project
Budget Grant 2024-25 (In Crores of Rs)
1
Angul-Sukinda Road (98.7 km) New line
0.01
2
Haridaspur-Paradeep (82km)New line
0.20
3
Khurda Road-Bolangir (289 km) New line
1350.00
4
Talcher-Bimlagarh (154 km) New line
500.00
5
Jeypore-Malkangiri (130 KM)
223.00
6
Jeypore-Nabarangpur(38Km.)
235.00
7
Naupada–Gunupur-New Broad gauge line up to Theruvali (79.15 KM)
50.00
8
Gandhmardhan Iron Ore mines to Goaldih Railway station
20.00
9
Kondinga mali Bauxite Mines to Singaram Railway Station